525/69 kV Atlas North Collector Substation (Solar + BESS)

Client: Confidential
Dates: June 2026 – September 2026
Duration: 3 months
Location: La Paz County, Arizona, USA

The project involved a new 525/69 kV collector substation for a utility-scale solar and battery energy storage system (BESS) facility in western Arizona, interconnected at 525 kV to a nearby 500 kV switchyard. Gridwise Engineering provided senior engineering review of the preliminary substation physical design package, and then updated the drawings to meet 500 kV design requirements. The substation has three 525/69 kV, 264/352/440 MVA power transformers, each with its own 550 kV SF6 breaker. On the low side is a 69 kV bus with main breakers, switched capacitor banks and collector feeder positions serving PV, BESS and BESS auxiliary loads.

Highlights & Services

  • Senior review of the complete substation physical design package: general arrangement, elevations, bus details, shielding, grounding, fencing, cable trench, conduit and control enclosure layouts.

  • Update of the drawing package for 525 kV (1,800 kV BIL) clearances, including phase-to-phase, phase-to-ground and ground clearance checks throughout the 525 kV and 69 kV yards.

  • 525 kV conductor and bus assessment, including a review of voltage gradient and corona performance per IEEE 605 and conductor upsizing.

  • Rigid bus design recommendations: replacing flexible conductor spans with aluminum tubular bus, checking span lengths and overhangs with rigid bus calculations, and adding independent bus supports at transformer neutral connections.

  • 69 kV yard optimization: solid-bus connections between the high and low buses, feeder conductor rationalization, surge arrester mounting to improve clearances, and capacitor bank and transformer neutral bus arrangements.

  • Equipment integration of 550 kV and 72.5 kV SF6 breakers, CVTs, VTs, neutral grounding reactors, capacitor banks and capacitor switchers.

  • Scope-gap identification for the next design stage: additional elevations, NGR and bus installation details, conduit schedules and individual equipment grounding details.

Utility-scale solar and battery energy storage facility with 525/69 kV collector substation, Arizona