Generator Interconnection Studies and Conceptual Designs
Client: Various
Dates: 2024 – Present
Duration: Typically 1–2 months each
Location: Various locations, BC, Canada
Gridwise Engineering provided conceptual substation design, transmission interconnection PSS®E studies and engineering support for a number of wind farm and solar developers responding to BC Hydro's 2024 and 2025 Call for Power, and for other developers looking to connect to the grid within BC. Each assignment typically runs one to two months.
Highlights & Services
Interconnection studies for new wind farms connected to the BC Hydro grid, including active and reactive power flow at the point of interconnection, fault levels and confirmation of generator response to dynamic system conditions.
Conceptual design for multiple collector substations for BC Hydro Call for Power proponents.
Conceptual design for solar facilities connecting to the FortisBC grid, including an agrisolar facility at an Okanagan winery.
Reactive power flow and fault study analysis, with PSS®E and PSCAD modelling.
Recommendation of reactive power equipment to maximize delivery at the point of interconnection and meet BC Hydro requirements.
Electrical, civil, structural and protection and control substation preliminary designs, including single line diagrams, preliminary station layouts and protection and control single line diagrams.
Preliminary equipment specifications and coordination with equipment vendors.
Coordination with BC Hydro to support Feasibility and System Impact Study inputs, including continued work with a successful Call for Power proponent to refine their design for the System Impact Study.