FortisBC Beaver Valley Substation 63/25 kV Electrical Design
Client: FortisBC
Dates: November 2025 – June 2026
Duration: 6 months
Location: Trail, BC, Canada
FortisBC received BC Utilities Commission approval to construct a new 63/25 kV substation in Fruitvale, BC, driven by the condition of aging infrastructure at the existing Fruitvale and Hearns substations and the resulting risk to supply reliability in the surrounding area. Gridwise Engineering was engaged to take over the Electrical Design from the incumbent consultant and drive the 133-drawing package through to Issued for Construction. Gridwise re-baselined the entire set into a single coordinated package, closed out the outstanding review comments from the previous design, and completed the design through 60% and 90% IFR to meet FortisBC's critical IFC date.
Highlights & Services
Assumed the Electrical / P&C design from the previous engineering service provider mid-stream and re-baselined 133 drawings at four different levels of completion into one coordinated IFC package.
Schematics and wiring diagrams for 63 kV line primary and standby protection, 63/25 kV T1 and T2 transformer primary and standby protection, metering and control, and 25 kV feeder protection and metering.
DC schematics for the 63 kV circuit breakers and motorized disconnect switches, the 27 kV main and tie breakers, and the 27 kV feeder breakers, including 50/51 and feeder metering.
P&C, I/O, VT junction box, lighting contactor and battery room ventilation panel layouts, with wiring diagrams for eight new P&C panels, the SCADA/COMM panel, I/O panels and all switchyard equipment.
AC and DC station service single line diagrams, cable schedule, operating limits diagram, RTU/SCADA schematics, annunciator schematics, and security and fire alarm schematics.
Preparation of 100 equipment manufacturers' drawings (9000 series), station material list and work summary.
Interface with the completed physical design, removal of engineering holds based on the existing design, and completion of design components to resolve issues with the existing design.