345/34.5 kV 600 MVA Data Center Substation

Client: Confidential
Dates: May 2026 – August 2026
Duration: 4 months (in progress)
Location: Reno, Nevada, USA

The project involves a new 345/34.5 kV substation at a Nevada data center campus, interconnected to the local utility at 345 kV. Gridwise Engineering has been subcontracted to complete packages for the Electrical and Protection & Control design for the prime consultant. The substation includes a 345 kV breaker-and-a-half scheme with two incoming lines feeding five 345/34.5 kV transformers (90/120/150 MVA), with indoor 34.5 kV feeds to switchgear distributing to data center feeders. Total station capacity is approximately 600 MW with N+1 redundancy.

Highlights & Services

  • Engineering design for discrete packages within the new substation.

  • Review of the AIS 345/34.5 kV substation layout, sections and details.

  • Protection and control design using SEL relays: SEL-411L dual line current differential for the 345 kV lines, SEL-487E dual-zone transformer and bus differential, SEL-351S for 345 kV breaker failure and 34.5 kV bus overcurrent protection, and SEL-751 for 34.5 kV feeder and tie protection.

  • Completion of all P&C and SCADA schematics, panel layouts and wiring (over 400 drawings) in a three-month period.

  • Coordination with the prime consultant's electrical, architectural, civil and structural design.

  • Lighting study and lighting arrangement.

  • SCADA and communications design (SEL RTAC, redundant fiber optic paths) and integration of all protection functions into the station data acquisition system.

345/34.5 kV 600 MVA data center substation campus, Reno, Nevada