Shell Montney Electrification 230/25 kV Substation

Client: Shell Canada
Dates: August 2023 – December 2024
Duration: 17 months
Location: Fort St. John, BC, Canada

Shell Canada required a new 230 kV load interconnection with BC Hydro to electrify its Groundbirch Montney gas plant, replacing natural gas-driven compressors with electric compressors to significantly reduce emissions from fuel combustion. The initiative is projected to reduce emissions by 1,077,099 tCO2e through 2032.

Gridwise Engineering completed the detailed Electrical and Protection & Control design for the new 230/25 kV substation, including all equipment specifications, equipment reviews, detailed design drawings, calculations, factory acceptance testing, relay settings and programming, and construction and commissioning support. The substation includes a 230 kV incoming line interconnected to BC Hydro, two 230/25 kV 50/66.6/83.3 MVA power transformers, three 230 kV circuit breakers (two with point-on-wave control) and 25 kV indoor metal-clad switchgear. It was put into service in December 2024.

Highlights & Services

  • Equipment specification, equipment drawing and document review, factory acceptance testing, and review and acceptance of all site commissioning tests and POR sign-off for the equipment.

  • Protection philosophy, protection coordination and relay settings study, implementation of BC Hydro-mandated protection and control for the facility, and coordination with BC Hydro protection schemes.

  • Enhanced the preliminary design with industry best practices for safety, fully endorsed by the client, and updated the design to address the facility's operational requirements.

  • Integration of the new substation and switchgear with the existing gas plant.

  • Coordination with the civil and structural design teams, and with the transmission and distribution line engineers connecting to the new substation.

  • Coordination with BC Hydro (the interconnecting utility) to meet transmission line interconnection and protection and control requirements.

  • Preparation of the energization plan and switching orders, coordinated with BC Hydro, and POR sign-off for the energization and commissioning of the customer's facility.